Question 41

During project execution you found out that work is often not performed at the right time and in the right order. Deliverables are made by one team member that cannot be processed by another one. This already leads to timely rework and bad morale among team members.
Which project management tool is most appropriate to deal with problems like this?

A. Organization chart
B. RACI matrix
C. Communications management plan
D. Work authorization system
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
vikram_unde
Contributor
Contributor
Posts: 185
Joined: Tue Aug 23, 2016 5:48 am

Re: Oliver 175 - 41st Question

Postby vikram_unde Fri Dec 23, 2016 11:52 am

D. Work authorization system
Housam Bassal
Contributor
Contributor
Posts: 239
Joined: Fri Nov 04, 2016 7:38 pm

Re: Oliver 175 - 41st Question

Postby Housam Bassal Fri Dec 23, 2016 5:34 pm

Correct answer is D

Work Authorization System. A subsystem of the overall project management system. It is a collection of formal documented procedures that defines how project work will be authorized (committed) to ensure that the work is done by the identified organization, at the right time, and in the proper sequence. It includes the steps, documents,
tracking system, and defined approval levels needed to issue work authorizations.
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
jyotimayank
Expert
Expert
Posts: 504
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 41st Question

Postby jyotimayank Thu Dec 29, 2016 10:13 am

Yes Housam the correct answer is option D.

Refer to page 567 of PMBOK® Guide 5th Edition
Work Authorization System is a collection of formal documented procedures that defines how project work will be authorized to ensure the work is done by right person, at right time, in proper sequence.


Systems which are defined at organization level falls under EEF (Enterprise Environmental Factors), because they are not project specific system, they limits your project execution, like if WAS requires some set of approvals, project team has to plan for them, you can not change Work Authorization System(WAS) for a given project. The work authorization system is a subsystem of the overall project management system, and project management system also falls under EEF.

You can refer to the following link for more insight of this topic
Enterprise Environmental Factors Vs. Organization Process Assets
http://www.izenbridge.com/blog/enterpri ... ss-assets/
Video
http://www.izenbridge.com/videogallery/ ... -part-2-2/