Which is not a type of project review meeting?
o Team review meetings
o Project status meetings
o Executive management review meetings
o Customer review meetings

Answer given is b. Why is that?
manishpn
Expert
Expert
Posts: 2150
Joined: Sat Jan 04, 2014 3:55 pm

Re: Oliver 175- 157th question

Postby manishpn Thu Dec 22, 2016 1:21 pm

there are 2 ways to approach this question.
simplest way is elimination -
all options provided has review word in it. except option B
Second way is look at definition

o Team review meetings - Although not mentioned in PMBOK This is a meeting where project team review is held which is indirectly projects review
o Project status meetings - this meeting there is no review its more of status and this can happen every day or week depending on need.
o Executive management review meetings - in this meeting executive management will review project
o Customer review meetings - this meeting customer will review project
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/