Postby jyotimayank Tue Dec 20, 2016 2:21 pm

Question 36

You recently took over the assignment for a project. The project charter has been developed. What is an appropriate next step for you?

A. Develop the risk register.
B. Develop the project milestone schedule.
C. Develop management plans.
D. Get approval for the project management plan.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Housam Bassal
Contributor
Contributor
Posts: 239
Joined: Fri Nov 04, 2016 7:38 pm

Re: Oliver 175 - 36th Question

Postby Housam Bassal Tue Dec 20, 2016 6:31 pm

After Develop the project charter had been done , the next step is to develop the project management plan with its subsidiaries. Hence the correct answer is C.
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
jyotimayank
Expert
Expert
Posts: 502
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 36th Question

Postby jyotimayank Fri Dec 23, 2016 10:43 am

Yes Housam you are right, the correct answer is option C.

Refer to page 72 of PMBOK® Guide 5th Edition

Project charters are often used as a means to introduce a project to the organization. This document outlines the high-level project description, the business opportunity or need, and the project’s purpose. Project charter and the requirements documentation is used during the Define Scope process, resulting in project scope statement. Followed by the process of breaking down the work of the project via a work breakdown structure (WBS). Tasks are accomplished in the Create WBS process. The WBS defines the scope of the project and breaks the work down into components that can be scheduled and estimated as well as easily monitored and controlled. The Develop Project Management Plan process brings all these subsidiary plans together, along with the outputs of the Planning group processes, into one document called the project management plan.
The inputs to Develop Project Management Plan include project charter, outputs from planning processes.


You can refer to the following link for more insight of this topic
http://www.izenbridge.com/blog/develop- ... -planning/