Question 28


28. You are in the process of planning a project and found that stakeholders often have varying objectives and requirements. This makes it hard to come up with a
plan with which all objectives will be met. What is probably most helpful to ensure common understanding?

A. Ask the project stakeholders to build focus groups in order to discuss and remedy conflicting interests.
B. Create an exhaustive document describing your point of view and ask stakeholders to review it.
C. Let each stakeholder write a statement of work, merge the documents to a project scope statement.
D. Use your authorization as the project manager to clearly prioritize the different objectives.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
vikram_unde
Contributor
Contributor
Posts: 185
Joined: Tue Aug 23, 2016 5:48 am

Re: Oliver 175 - 28th Question

Postby vikram_unde Fri Dec 16, 2016 1:43 pm

A or D

I will go with D. Use your authorization as the project manager to clearly prioritize the different objectives.

Option A - Don't think its good to "ask" stakeholder to create focus groups. Instead PM should create focus groups and facilitate consensus. I believe, instead of focus groups, facilitated workshop is good choice.
jyotimayank
Expert
Expert
Posts: 504
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 28th Question

Postby jyotimayank Mon Dec 19, 2016 12:01 pm

The correct answer is option A.

Refer to page 31 of PMBOK® Guide 5th Edition
Stakeholders have varying levels of responsibility and authority when participating on a project. Their involvement may range from occasional contributions in surveys and focus groups to full project sponsorship which include providing financial and other support.


The primary difference between focus groups and facilitated workshops are that focus groups are gatherings of prequalified subject matter experts and stakeholders and facilitated workshops consist of cross-functional stakeholders who can define cross-functional requirements. Differences among stakeholders can be resolved more quickly and consensus is more easily attained in a facilitated workshop environment.

You can refer to the following link for more insight of this topic
http://www.izenbridge.com/videogallery/ ... anagement/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “Oliver 175 PMP Questions”

Who is online

Users browsing this forum: Yahoo [Bot] and 2 guests