Question 22

Which statement describes best handling of assumptions during the initiating
processes?

A. It is the responsibility of the sales person in charge to identify all risks related to a customer project.
B. Managing and organizing assumptions means avoiding risks right from the start of the project.
C. Organizational, environmental and external assumptions should be addressed by the project charter.
D. Risks are a sign of uncertainty. Avoiding all uncertainties means that a project should have no risks at all.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
vikram_unde
Contributor
Contributor
Posts: 185
Joined: Tue Aug 23, 2016 5:48 am

Re: Oliver 175 - 22nd Question

Postby vikram_unde Thu Dec 15, 2016 2:10 pm

C. Organizational, environmental and external assumptions should be addressed by the project charter
manishpn
Expert
Expert
Posts: 2453
Joined: Sat Jan 04, 2014 3:55 pm

Re: Oliver 175 - 22nd Question

Postby manishpn Thu Dec 15, 2016 3:37 pm

jyotimayank wrote:Question 22

Which statement describes best handling of assumptions during the initiating
processes?

A. It is the responsibility of the sales person in charge to identify all risks related to a customer project.
Sales person is not competent in project management and should be expected to focus on risks in project
B. Managing and organizing assumptions means avoiding risks right from the start of the project.
Avoiding risks is not a solution
C. Organizational, environmental and external assumptions should be addressed by the project charter.
D. Risks are a sign of uncertainty. Avoiding all uncertainties means that a project should have no risks at all.
Risks are to be managed cant be avoided
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
vikram_unde
Contributor
Contributor
Posts: 185
Joined: Tue Aug 23, 2016 5:48 am

Re: Oliver 175 - 22nd Question

Postby vikram_unde Thu Dec 15, 2016 3:46 pm

Hi Manish,

Do you mean answer is "A"?

You mentioned - Sales person is not competent in project management and should be expected to focus on risks in project

Can you please clarify - why sales person should focus on risks? Please let me know if I understood your response incorrectly.

Regards,
Vikram Unde
manishpn
Expert
Expert
Posts: 2453
Joined: Sat Jan 04, 2014 3:55 pm

Re: Oliver 175 - 22nd Question

Postby manishpn Mon Dec 11, 2017 8:59 pm

answer is C
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “Oliver 175 PMP Questions”

Who is online

Users browsing this forum: No registered users and 1 guest