Question 12

How should change management be planned for?

A. Changes are generally not predictable, therefore planning for change
management cannot be reasonable.
B. Planning for change management should be done while the various change
control processes are being applied.
C. Change management can be planned in a set of management plans or a
specific change management plan.
D. Changes are a sign of bad planning. One should avoid changes during a
project, thus eliminating the need to manage them.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
sarthy
Beginner
Beginner
Posts: 25
Joined: Sun Feb 22, 2015 2:44 pm

Re: Oliver 175 - 12th Question

Postby sarthy Wed Dec 14, 2016 12:58 pm

Confused between B and C
jyotimayank
Expert
Expert
Posts: 514
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 12th Question

Postby jyotimayank Thu Dec 15, 2016 12:46 pm

The correct answer is option C.

Refer to page 94 of PMBOK® Guide 5th Edition

Perform integrated change control allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.So change management must be planned in a set of management plan.

You can refer to the following link for more insight of this topic

http://www.izenbridge.com/videogallery/ ... anagement/