Oliver 175 - 94th question

thiru26@gmail.com
Contributor
Contributor
Posts: 242
Joined: Sun Sep 13, 2015 10:57 pm

Oliver 175 - 94th question

Postby thiru26@gmail.com Mon Oct 12, 2015 5:17 pm

94. Together with your team, you applied three-point estimation on a critical path which consists of two activities. The following duration uncertainties are all calculated assuming a ±3sigma confidence interval. The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire path?
o 21 days
o 30 days
o 42 days
o No statement is possible from the information given.
manishpn
Expert
Expert
Posts: 2428
Joined: Sat Jan 04, 2014 3:55 pm

Re: Oliver 175 - 94th question

Postby manishpn Mon Oct 12, 2015 6:12 pm

usually you wont get this type but see this thread

viewtopic.php?f=3&t=287&p=936
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
thiru26@gmail.com
Contributor
Contributor
Posts: 242
Joined: Sun Sep 13, 2015 10:57 pm

Re: Oliver 175 - 94th question

Postby thiru26@gmail.com Tue Oct 13, 2015 11:00 pm

Thanks Manish.