Q&A Risk management

rahul.kanugo
Posts: 11
Joined: Tue May 17, 2016 4:42 pm

Q&A Risk management

Postby rahul.kanugo Thu Jan 26, 2017 7:41 am

Risk managenet.PNG
Risk managenet.PNG (34.27 KiB) Viewed 420 times


Answer is B... please justify
manishpn
Expert
Expert
Posts: 2001
Joined: Sat Jan 04, 2014 3:55 pm

Re: Q&A Risk management

Postby manishpn Thu Jan 26, 2017 2:34 pm

This is not a very good quality question from Rita.

The best way to approach this is use elimination technique and when you do that option A, C and D makes little sense.

I am not fan of such questions as when you refer to stakeholders it can mean any party who has stake in project this includes risk team as well
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
rahul.kanugo
Posts: 11
Joined: Tue May 17, 2016 4:42 pm

Re: Q&A Risk management

Postby rahul.kanugo Sat Jan 28, 2017 8:30 am

thanks

Return to “Oliver 75 PMP Questions”

Who is online

Users browsing this forum: Bing [Bot] and 1 guest