Oliver 75 - 30th Question

jyotimayank
Expert
Expert
Posts: 535
Joined: Mon Mar 09, 2015 6:01 am

Oliver 75 - 30th Question

Postby jyotimayank Mon May 09, 2016 9:17 am

Question 30.
The scope baseline consists of what?

A. Scope statement, WBS, and WBS dictionary
B. Cost baseline, quality baseline and schedule baseline
C. Configuration management plan and configuration identification document
D. Procurement statement of work and project scope statement
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 30th Question

Postby Ananyapmp Mon May 09, 2016 11:35 am

A, scope statement plus wbs+ wbs dictionary
jyotimayank
Expert
Expert
Posts: 535
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 30th Question

Postby jyotimayank Tue May 10, 2016 7:49 am

Yes the correct answer is A.

PMBOK® Guide Fifth Edition defines Scope baseline as
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison. It is a component of the project management plan. Components of the scope baseline include Project Scope Statement, WBS and WBS Dictionary.


Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. WBS is an important component of scope baseline. WBS represents the total scope of work in hierarchical form. As we go down in hierarchy of WBS, each level represents a progressively detailed definition of project work.

Project scope statement includes the description of the project scope,major deliverables, assumptions, and constraints.

Work Breakdown Structure defines all the project and product deliverables in hierarchical form and gives an idea about which activities are need to planned, monitored and from which agreed point of WBS, cost of these activities will be tracking in company accounting system.

WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS.

Refer to Page 131-133 of PMBOK® Guide 5th Edition

For more insight of this topic refer to the following blog
What are the Differences between Work Package and Planning Package?

http://www.izenbridge.com/blog/what-are ... g-package/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 30th Question

Postby Ananyapmp Tue May 10, 2016 10:29 am

Thanks Jyoti

Return to “Oliver 75 PMP Questions”