Pragmatic Agile Workshop

Oliver 75 - 75th Question

jyotimayank
Expert
Expert
Posts: 501
Joined: Mon Mar 09, 2015 6:01 am

Oliver 75 - 75th Question

Postby jyotimayank Mon May 09, 2016 7:13 am

Question 75.

You have just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:

Which potential inconsistency in the diagram should you solve right now to ensure that the activities and the milestones "Start" and "A-F finished" are correctly linked?

A. Activity E is open ended (a "dangle") in relation to the finish milestone path convergence.

B. Activity F is open ended in relation to the path divergence after the start milestone.

C. You cannot calculate a critical path when lags and/or leads are calculated in percent.

D. Activities E to F need another task drawn as a hammock to calculate level of effort.
Attachments
75th question.jpg
75th question.jpg (19.91 KiB) Viewed 2232 times
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 75th Question

Postby Ananyapmp Mon May 09, 2016 11:10 am

A should be taken up first
manishpn
Expert
Expert
Posts: 2129
Joined: Sat Jan 04, 2014 3:55 pm

Re: Oliver 75 - 75th Question

Postby manishpn Mon May 09, 2016 2:26 pm

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
amolfuke
Contributor
Contributor
Posts: 119
Joined: Tue May 31, 2016 9:31 pm

Re: Oliver 75 - 75th Question

Postby amolfuke Sun Jul 17, 2016 3:02 am

Can I know the explanation of this ? I don't have access to the above thread.
manishpn
Expert
Expert
Posts: 2129
Joined: Sat Jan 04, 2014 3:55 pm

Re: Oliver 75 - 75th Question

Postby manishpn Sun Jul 17, 2016 7:25 am

yes relationship can be in % which means based on x% of predecessor the successor can start/finish depending on type of relationship
you cannot calculate critical path when relationship are in % and not absolute duration (e.g. days)
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Vigneshk
Posts: 2
Joined: Thu Feb 02, 2017 7:31 am

Re: Oliver 75 - 75th Question

Postby Vigneshk Wed Feb 08, 2017 11:23 am

Hi Manish - But the answer as per source is A. Any idea why ?

Return to “Oliver 75 PMP Questions”

Who is online

Users browsing this forum: No registered users and 2 guests