Oliver 75 - 64th Question

Postby jyotimayank Fri May 06, 2016 9:14 am

Question 64.

Which of the following statements describes best the relationship between project phases and the project life cycle?

A. The project life cycle includes the time when the project is performed and the expected product lifespan after that.

B. In project management, the sequence of project phases and phase gates is often referred to as project life cycle.

C. The project life cycle is regarded as a sequence of project activities while phases are defined to control overlapping activities.

D. The project life cycle describes how iterations of project management processes are used when a project schedule is developed.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 64th Question

Postby Ananyapmp Fri May 06, 2016 12:46 pm

May be B
jyotimayank
Expert
Expert
Posts: 535
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 64th Question

Postby jyotimayank Wed May 11, 2016 5:49 am

Yes the correct answer is B.

PMBOK® Guide Fifth Edition defines Characteristics of the Project Life Cycle as

Projects vary in size and complexity. All projects can be mapped to the following generic life cycle structure-> Starting the project, Organizing and preparing, Carrying out the project work, and Closing the project.
A project may be divided into any number of phases. A project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables.


The phase structure allows the project to be segmented into logical subsets for ease of management, planning, and control. The number of phases, the need for phases, and the degree of control applied depend on the size,complexity, and potential impact of the project. The closure of a phase ends with some form of transfer or hand-off of the work and is known as phase gate.

Refer to Page 38-42 of PMBOK® Guide 5th Edition

For more insight of this topic refer to the following blog and video

Video : Project Life Cycle | PMBOK 5 | Lesson 2
http://www.izenbridge.com/videogallery/ ... -part-4-2/

Webinar : Selecting Right Project Life Cycle?
http://www.izenbridge.com/webinars/sele ... ife-cycle/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd