Oliver 75 - 57th Question

Postby jyotimayank Fri May 06, 2016 7:43 am

Question 57.

Which of the following is true regarding the code of accounts?

A. It allows one to easily identify the breakdown level of the item in the resource structure.

B. It describes the coding structure used by the performing organization to report financial information in its general ledger.

C. It is the collection of unique identifiers generally assigned to WBS items.

D. It defines ethical behavior in the project and the responsibilities to the customer and the profession.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 57th Question

Postby Ananyapmp Tue May 10, 2016 11:19 am

Ans is C
jyotimayank
Expert
Expert
Posts: 504
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 57th Question

Postby jyotimayank Thu May 12, 2016 12:40 pm

The correct answer is C.

As per PMBOK® Guide 5th Edition

Code of Accounts is a numbering system used to uniquely identify each component of the work breakdown structure (WBS).
The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information.


A control account is a management control point where scope, budget, actual cost, and schedule are integrated and compared to the earned value for performance measurement.Each control account may include one or more work packages,and one or more planning packages.

Refer to Page 531 of PMBOK® Guide 5th Edition
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd