Question 52.

What is a constructive change?

A. A change request that helps improving the project and its product, service or result and is discussed generally in a friendly style.
B. A direction by the buyer or an action taken by the seller that the other party considers an undocumented change to the contract.
C. A field change or ad-hoc change mandated by the project customer in a public construction project.
D. A change request which will lead to the re-construction of an older version of the project performance baseline by the contractor.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 52nd Question

Postby Ananyapmp Fri May 06, 2016 12:38 pm

I think its A
jyotimayank
Expert
Expert
Posts: 504
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 52nd Question

Postby jyotimayank Wed May 11, 2016 1:05 pm

The correct answer is B.

PMBOK® Guide Fifth Edition defines

Constructive changes are those requested changes where the buyer and seller cannot reach an agreement on compensation for the change or cannot agree that a change has occurred. These contested changes are variously called claims, disputes, or appeals.


Changes which are not resolved can include direction provided by the buyer or actions taken by the seller, is considered as a constructive change to the contract. And any of these constructive changes may be disputed by one party and can lead to a claim against the other party.

Refer to Page 384-385 0f PMBOK® Guide 5th Edition
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Housam Bassal
Contributor
Contributor
Posts: 239
Joined: Fri Nov 04, 2016 7:38 pm

Re: Oliver 75 - 52nd Question

Postby Housam Bassal Mon Dec 19, 2016 7:42 pm

jyotimayank wrote:The correct answer is B.

PMBOK® Guide Fifth Edition defines

Constructive changes are those requested changes where the buyer and seller cannot reach an agreement on compensation for the change or cannot agree that a change has occurred. These contested changes are variously called claims, disputes, or appeals.


Changes which are not resolved can include direction provided by the buyer or actions taken by the seller, is considered as a constructive change to the contract. And any of these constructive changes may be disputed by one party and can lead to a claim against the other party.

Refer to Page 384-385 0f PMBOK® Guide 5th Edition


Is there any webinar, video, or blog related to this topic?
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
jyotimayank
Expert
Expert
Posts: 504
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 52nd Question

Postby jyotimayank Tue Dec 20, 2016 7:25 am

Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd