Question 45.
What does the acronym RACI commonly stand for in project management?

A. Responsible, Accountable, to be Consulted, to be Informed
B. Remote, Attached, Connected, Integrated
C. Risk Analysis and Caution Initiative
D. Randomly Accessible Cash flow Information
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 45th Question

Postby Ananyapmp Fri May 06, 2016 12:26 pm

Its A.
jyotimayank
Expert
Expert
Posts: 535
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 45th Question

Postby jyotimayank Fri May 06, 2016 2:32 pm

Yes the correct answer is A.

RACI means
Responsible
Accountable
Consult
Inform
RACI chart is a useful tool to use when the team consists of internal and external resources in order to ensure clear divisions of roles and expectations.
It is especially useful in clarifying roles and responsibilities in cross-functional/departmental projects and processes.

Refer to Page 262 0f PMBOK® Guide 5th Edition
As per PMBOK
A responsibility assignment matrix (RAM) is a grid that shows the project resources assigned to each work package. It is used to illustrate the connections between work packages or activities and project team members. RACI chart is an example of RAM


For more insight of this topic refer to the following video

http://www.izenbridge.com/videogallery/ ... 3-pmbok-5/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Ananyapmp
Beginner
Beginner
Posts: 45
Joined: Fri Apr 22, 2016 11:25 am

Re: Oliver 75 - 45th Question

Postby Ananyapmp Mon May 09, 2016 11:37 am

Thanks for detailed description.