Oliver 75 - 20th Question

jyotimayank
Expert
Expert
Posts: 516
Joined: Mon Mar 09, 2015 6:01 am

Oliver 75 - 20th Question

Postby jyotimayank Wed Apr 13, 2016 1:39 pm

20. A project management team wants to procure some customized products which are available in identical grade and quality from many vendors. What should be included in the procurement package to ensure that their offers will be comparable?

A. A statement of work describing the needs of the project in sufficient detail to enable vendors to make suitable proposals
B. A statement of work specifying attributes and metrics of the requested deliverables in detail to allow vendors submission of bids
C. The approved project scope statement, the WBS which should be broken down to work package level and the WBS dictionary
D. The risk management plan and the reports from those risk management reviews which have been made so far
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
jyotimayank
Expert
Expert
Posts: 516
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 20th Question

Postby jyotimayank Fri Apr 15, 2016 12:41 pm

The correct answer is B.

The buyer structures procurement documents to facilitate an accurate and complete response from all the prospective sellers. These documents include description of response , the relevant procurement statement of Work and contractual provisions.

Refer to Page 367-368 (12.1.3.3 2nd phrase) 0f PMBOK® Guide 5th Edition.

For more insight of this topic refer to the following webinar

http://www.izenbridge.com/videogallery/ ... e-webinar/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd