A project manager spent some days to create a multi-page document, which he called project charter. The document should have been issued by the project sponsor. The sponsor found the document outsized and asked for a condensed document.
Which of the following is usually not an element of the project charter?

A. The authority level of the project manager
B. Detailed control account and work package descriptions
C. The business need that the project was undertaken to address
D. High-level risks
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Atg1000
Posts: 14
Joined: Sun Feb 14, 2016 1:40 am

Re: Oliver 75 - 6th Question

Postby Atg1000 Wed Apr 13, 2016 9:41 am

B. Detailed control account and work package descriptions.
jyotimayank
Expert
Expert
Posts: 518
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 6th Question

Postby jyotimayank Wed Apr 13, 2016 12:58 pm

Yes the correct answer is B.

Project charter is a document which gives recognition to the existence of the project, and designates the project manager, and also provides project manager an authority to allocate organizational resources for the project goal.
Work Breakdown Structure defines all the project and product deliverables in hierarchical form, control account and work packages are part of scope management plan.

Refer to Page 67 to 72 0f PMBOK® Guide 5th Edition
For more insight of this topic refer to the following blogs

http://www.izenbridge.com/blog/develop- ... -planning/

http://www.izenbridge.com/blog/what-are ... g-package/