Oliver 75 - 14th Question

jyotimayank
Expert
Expert
Posts: 514
Joined: Mon Mar 09, 2015 6:01 am

Oliver 75 - 14th Question

Postby jyotimayank Wed Mar 30, 2016 1:17 pm

Question 14.
A project management team has subcontracted work to a service company. Which of the following tools is the best choice to assure that this company will be able to meet the quality requirements of the project?
A. Quality audit
B. Deliverable inspection
C. Fixed price contract
D. Service level agreement
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
EsakkiMuthu
Contributor
Contributor
Posts: 191
Joined: Tue Oct 06, 2015 6:11 pm

Re: Oliver 75 - 14th Question

Postby EsakkiMuthu Wed Mar 30, 2016 7:14 pm

Quality audit
Regards
Esakki
PMI-ACP, PMP
jyotimayank
Expert
Expert
Posts: 514
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 14th Question

Postby jyotimayank Wed Apr 13, 2016 1:17 pm

Yes the correct answer is A.

Quality Audit is to verify quality of processes, to seek improvement, identify best practices, reduce overall cost of quality, confirm implementation of approved changes, need quality documentations.


Refer to Page 247 0f PMBOK® Guide 5th Edition

For more insight of this topic refer to the following blog

http://www.izenbridge.com/blog/differen ... l-quality/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd