Question 12.
Which should be included in a requirements management plan?
A. The document should trace requirements to project scope / WBS deliverables.
B. It should describe how requirements activities will be planned, tracked, and reported.
C. It should trace high-level requirements to more detailed requirements.
D. It should trace requirements to business needs, opportunities, goals, and objectives.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
EsakkiMuthu
Contributor
Contributor
Posts: 191
Joined: Tue Oct 06, 2015 6:11 pm

Re: Oliver 75 - 12th Question

Postby EsakkiMuthu Wed Mar 30, 2016 7:17 pm

B
Regards
Esakki
PMI-ACP, PMP
jyotimayank
Expert
Expert
Posts: 514
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 12th Question

Postby jyotimayank Wed Apr 13, 2016 7:14 am

Yes the correct answer is option B.

Requirement Management Plan is a component of project management plan that state how the requirement is analyzed, documented and managed.

Reference: PMBOK® Guide Fifth Edition, page 110, 5.1.3.2


For more insight of this topic refer to the following blog and video
Blog
http://www.izenbridge.com/blog/requirem ... e-need-it/
Video
https://www.youtube.com/watch?v=hzzVmFm ... e=youtu.be
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “Oliver 75 PMP Questions”

Who is online

Users browsing this forum: No registered users and 1 guest