Question 4
Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives. Which stage of team development can be difficult to overcome in such a situation?
A. Storming from Forming, Storming, Norming, Performing
B. Panic from Enthusiasm, Panic, Hope, Solution
C. Kickoff from Assignment, Kickoff, Training, Communicating
D. Frustration from Direction, Frustration, Cooperation, Collaboration
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
EsakkiMuthu
Contributor
Contributor
Posts: 191
Joined: Tue Oct 06, 2015 6:11 pm

Re: Oliver 75 - 4th Question

Postby EsakkiMuthu Wed Mar 30, 2016 7:54 pm

A
Regards
Esakki
PMI-ACP, PMP
jyotimayank
Expert
Expert
Posts: 518
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 75 - 4th Question

Postby jyotimayank Mon Apr 04, 2016 7:57 am

Yes , the correct answer is option A.

Storming stage is the most critical stage with least productivity, so this stage needs to be closely monitored.
Project Manager's effort should be to resolve conflicts and pro-actively provide an environment of trust. This phase takes maximum time to overcome.

Refer to page 276 of PMBOK® Guide 5th Edition
For more details of this topic please visit the following link

http://www.izenbridge.com/videogallery/ ... zenbridge/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “Oliver 75 PMP Questions”

Who is online

Users browsing this forum: No registered users and 1 guest