Oliver 75 - 11th Question
SPI/CPI question
You found the following earned value analysis information for a project that was recently closed-out:
SPI = 0.7, CPI = 1.0
The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule but on budget.
The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
The project's deliverables have all been finished. The project came in on schedule but over budget.
Please suggest.
SPI = 0.7, CPI = 1.0
The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule but on budget.
The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
The project's deliverables have all been finished. The project came in on schedule but over budget.
Please suggest.
Re: SPI/CPI question
I went with B but the correct answer given is "A" . That what i was wondering , how can we say that the project was cancelled. This is from Oliver 75 questions.
Any further view from other friends ?
Any further view from other friends ?
- bhuvanpanwar1983
- Contributor
- Posts: 160
- Joined: Tue Jun 30, 2015 2:24 pm
Re: SPI/CPI question
you are right Ans A is the right choice.
Re: SPI/CPI question
Thanks a lot for answer . Make sense.
Re: SPI/CPI question
Sorry I misread the question.. correct answer is A -The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
Re: SPI/CPI question
this mean ???
if ...... SPI=1
deliverables are complete....
Can any body Explain ?
if ...... SPI=1
deliverables are complete....
Can any body Explain ?
Re: SPI/CPI question
"The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value. It measures how efficiently the project team is using its time. An SPI value less than 1.0 indicates less work was completed than was planned. An SPI greater than 1.0 indicates that more work was completed than was planned." (PMBOK 219)
SPI=1 implies that your project is on time
SPI=1 implies that your project is on time
- suhail1097@gmail.com
- Beginner
- Posts: 24
- Joined: Mon Sep 21, 2015 6:26 am
Oliver 75 - 11th Question
You found the following earned value analysis information for a project that was recently closed-out:
SPI = 0.7, CPI = 1.0
and its answer is " The project has been cancelled while it was executed. At that time the project was behind schedule and on budget."
How we came to project was cancelled in place of finished or closed
pls assist
thanks,
Suhail
SPI = 0.7, CPI = 1.0
and its answer is " The project has been cancelled while it was executed. At that time the project was behind schedule and on budget."
How we came to project was cancelled in place of finished or closed
pls assist
thanks,
Suhail
Re: Oliver 75 question
May refer this thread to start with : viewtopic.php?f=31&t=3041
- jyotimayank
- Expert
- Posts: 507
- Joined: Mon Mar 09, 2015 6:01 am
Re: Oliver 75 - 11th Question
The correct answer is option A.
The Scheduled Performance Index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value. SPI= EV/PV
The Cost Performance Index (CPI) is a measure of cost efficiency expressed as the ratio of earned value to actual cost. CPI= EV/AC
Refer to Page 219 0f PMBOK® Guide 5th Edition
For more insight of this topic refer to the following blog
http://www.izenbridge.com/blog/how-to-c ... pi-trends/
The Scheduled Performance Index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value. SPI= EV/PV
The Cost Performance Index (CPI) is a measure of cost efficiency expressed as the ratio of earned value to actual cost. CPI= EV/AC
Refer to Page 219 0f PMBOK® Guide 5th Edition
For more insight of this topic refer to the following blog
http://www.izenbridge.com/blog/how-to-c ... pi-trends/
Jyoti Gupta
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd
Re: Oliver 75 - 11th Question
Still could not understand how recently closed-out meant by Cancelled of project.
- Prembalaji
- Participant
- Posts: 69
- Joined: Wed May 10, 2017 1:38 pm
Re: Oliver 75 - 11th Question
Keyword is "CLOSED-OUT"
Dictonary meaning is Terminated / In-adequet / Exhausted
Hope this info helps
Dictonary meaning is Terminated / In-adequet / Exhausted
Hope this info helps
Cheers,
PJ
PJ
Return to “Oliver 75 PMP Questions”
Who is online
Users browsing this forum: No registered users and 1 guest