Oliver 75 - 18th Question

oberoi.amit
Contributor
Contributor
Posts: 125
Joined: Mon Mar 24, 2014 5:14 am

Oliver 75 - 18th Question

Postby oberoi.amit Wed Jul 16, 2014 3:32 am

Question from Oliver Lehmann

Q. Start dates in the following network logic diagram are defined as early morning, finish dates are evening.
If tasks are scheduled to begin at early start date, what is true?

Time Mgmt.PNG
Time Mgmt.PNG (32.8 KiB) Viewed 1552 times


Activity B has a free float of 10 d.
Activity B has a total float of 10 d.
Activity A has a free float of 10 d.
Activity A has a total float of 10 d.


Answer to this is Activity B has a total float of 10 d.

IT also has Free float of 10 because if it delays by 10 days successor will not be delayed.

Am I correct.
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Time Management

Postby namita Wed Jul 16, 2014 4:48 am

Now your understanding looks correct but the network diagram given is looking partial part of full diagram. Assuming that this is a partial diagram, end is not correctly shown and we don't have full end to end visibility, what we can surely say is Total Float of B is definitely 10. Free float can be different if B has other successors or other constraints not shown in the diagram

Worth going through my blog at below link

http://www.izenbridge.com/blog/what-is- ... ree-float/
oberoi.amit
Contributor
Contributor
Posts: 125
Joined: Mon Mar 24, 2014 5:14 am

Re: Time Management

Postby oberoi.amit Wed Jul 16, 2014 5:00 am

So you mean to say it is correct that we have total float and free float of 10 in this case...
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Time Management

Postby namita Wed Jul 16, 2014 5:12 am

If this is the full network and B is NOT having any other successor or constraints