Which term best describes an Agile project's approach to risk analysis?
A. Regression
B. Pareto
C. Qualitative
D. Monte Carlo

I think ans should be C but in one of the free question bank it's showing D.

http://www.exams.wyszukiwarka.c0.pl/en/ ... 33635.html


What is the correct ans?
seema.sonkiya
Expert
Expert
Posts: 1706
Joined: Fri Jul 11, 2014 11:57 am

Re: Risk Analysis in Agile

Postby seema.sonkiya Mon Jun 26, 2017 5:15 am

Agile never prescribe methods of doing Risk Analysis. Agile Manifesto says four values and 12 principles. According to these values, you need to figure out various methods like for prioritization, estimation and risk analysis.
If your actions are aligned with four values and 12 principles, you are Agile; Agile does not give any prescriptions of doing how to do risk analysis, Because best methods depend on your project context. If a fix prescription is there you are no more Agile.