Risk-Adjusted Blocklog priority

Postby evamahk Wed Nov 30, 2016 7:34 am

Dear all,
A very general problem of user story priority

should High-Value, High-Risk do first?
Or High-Value, Low-Risk do first?

It is difficult to choose.
should we choose based on Value level?? or based on Risk level???

please help to clarify..
thanks you
seema.sonkiya
Expert
Expert
Posts: 1533
Joined: Fri Jul 11, 2014 11:57 am

Re: Risk-Adjusted Blocklog priority

Postby seema.sonkiya Wed Nov 30, 2016 9:59 am

In general, we choose a high-value and high-risk items first. It gives early predictability and fast value realization.
User avatar
saket
Site Admin
Site Admin
Posts: 3079
Joined: Sat Dec 07, 2013 10:37 pm

Re: Risk-Adjusted Blocklog priority

Postby saket Sun Dec 04, 2016 8:53 am

Interesting question and we do not have any agreement in agile community about how the prioritization should be done, but as far as PMI ACP exam is concern we can clearly go with doing prioritization based on Value and Risk, so the item which are high in Value and High in Risk should be done first. This concept is coming from the book Agile Estimation and Planning by Mike Cohn.

This is how it is presented

Risk-Value.png
Risk-Value.png (10.57 KiB) Viewed 320 times


Hope this clarifies your question.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
evamahk
Posts: 10
Joined: Mon Nov 28, 2016 6:05 am

Re: Risk-Adjusted Blocklog priority

Postby evamahk Mon Dec 05, 2016 3:30 am

Thanks you saket.

Marking Very Clear for the exam.