There is a term of 'approved iteration', that's stakeholders approved the product increment of that iternation.
What's will happen if stakeholders not approved.
What's the action for the Agile coach to do?
What will happen if Iterations is not approved
- seema.sonkiya
- Expert
- Posts: 1994
- Joined: Fri Jul 11, 2014 11:57 am
Re: What will happen if Iterations is not approved
Where did you find the term approved iteration? In which agile approach are you using the term "approved iteration"?
What is the source of this question?
What is the source of this question?
Thanks & Kind Regards,
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Re: What will happen if Iterations is not approved
Approved Iteration.
it is in the PMI-ACP Examination Content Outline, Page 14, Tool & Techniques, Metric.
please advise how to deals with this situation.
thanks you.
it is in the PMI-ACP Examination Content Outline, Page 14, Tool & Techniques, Metric.
please advise how to deals with this situation.
thanks you.
- seema.sonkiya
- Expert
- Posts: 1994
- Joined: Fri Jul 11, 2014 11:57 am
Re: What will happen if Iterations is not approved
Iterations are approved based on many factors like:
Priority of features
Available time to market and
Team Capacity
If Scrum approach is used, Product Owner makes sure iterations are approved as a result of collaboration with stakeholders and development team.
Anyways whatever approach is used, negotiations and collaboration are needed to the desired objective.
Priority of features
Available time to market and
Team Capacity
If Scrum approach is used, Product Owner makes sure iterations are approved as a result of collaboration with stakeholders and development team.
Anyways whatever approach is used, negotiations and collaboration are needed to the desired objective.
Thanks & Kind Regards,
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Re: What will happen if Iterations is not approved
In case of agile we focus on learning for mistakes, assuming you end up in a situation where team gives a demo to stakeholder and Product Owner and they find the content of iteration not good enough. So what does it mean , it mean you did not met the iteration goal, what you do about it? you discuss it in the retrospective meeting, team along with Product Owner need to find what best case be done to avoid this happening again.
So one line answer would be "work as team to ensure it does not happen again" . Agile Coach can facilitate that by asking powerful questions . Here is one interesting webinar recording of powerful question.
So one line answer would be "work as team to ensure it does not happen again" . Agile Coach can facilitate that by asking powerful questions . Here is one interesting webinar recording of powerful question.