Please help me understand the logic for below question.Thanks.

Question: Team has just finished relative weighing of product backlog items for release, as shown in table below. Relative benefits carry weightage twice compared to relative penalty. Please rank these product features in order of decreasing priority.

2,1,3,5,4

3,5,1,2,4

2,3,5,4,1

Cannot conclude from given information

Ans: 2,1,3,5,4
Attachments
Question.png
Question.png (23.25 KiB) Viewed 1247 times
dsnglaa
Beginner
Beginner
Posts: 27
Joined: Sun Apr 03, 2016 5:10 am

Re: Query

Postby dsnglaa Wed Aug 03, 2016 2:13 pm

It is calculated based on Karl W model.

Priotiy = Value%/Cost%

eg. Feature 2

16/10 = 1.6
19/12 = 1.5 and so on..

Hope it helps!
sanjaykumar
Expert
Expert
Posts: 94
Joined: Thu Oct 29, 2015 8:46 am

Re: Query

Postby sanjaykumar Fri Aug 05, 2016 12:35 pm

While you may want to explore this topic from learning perspective, please feel free to skip it for PMI-ACP prep.
I am very positive you will not see such a question. :-)
Sanjay Kumar
Agile Trainer & Coach
sukanya.kambhampati
Posts: 3
Joined: Thu Jul 21, 2016 7:39 am

Re: Query

Postby sukanya.kambhampati Thu Aug 11, 2016 9:44 am

Thanks for the response and inputs.This helps.