When is the best time to start estimating the costs for an Agile project?
seema.sonkiya
Expert
Expert
Posts: 1807
Joined: Fri Jul 11, 2014 11:57 am

Re: estimating the costs for an Agile project

Postby seema.sonkiya Tue Jul 12, 2016 9:05 am

In genernall estimation is done at initial stage of the project when large number of stories are identified. Cost Estimation is continuous process as when new stories get identified during an iteration.

Team decides when and how to do estimation sessions during iteration.
dsnglaa
Beginner
Beginner
Posts: 27
Joined: Sun Apr 03, 2016 5:10 am

Re: estimating the costs for an Agile project

Postby dsnglaa Tue Jul 12, 2016 2:50 pm

Seema,

Is it before release planning meeting or after release planning ?
sarawat
Contributor
Contributor
Posts: 188
Joined: Wed Jul 08, 2015 9:24 am

Re: estimating the costs for an Agile project

Postby sarawat Wed Jul 13, 2016 3:51 am

budget is estimated during release planning. [ Release level ]
there are several metrics which are being used such as

1. The number of planned sprints in the release
2. The length of each sprint in calendar days
3. The number of story points planned for the release
4. The budget planned for the release
5. Start date of the project

6. Expected % Complete Number of sprints / Total number of sprints planned
7. Actual Cost to date
8. Cumulative story points completed This measures the total amount of work completed for the release as of that sprint boundary.
9. Net Story points added

Thanks n Regards,