Postby roylen Wed Feb 26, 2020 7:16 am

Hi Team,

I am going through the kanban video as a part of PMI-ACP.
Since we are accomodating urgent work in kanban board, is there any WIP limit for urgent work items in all the stages of kanban board.

Is estimation done for work items in kanban board.
seema.sonkiya
Expert
Expert
Posts: 2418
Joined: Fri Jul 11, 2014 11:57 am

Re: Kanban Board

Postby seema.sonkiya Fri Feb 28, 2020 11:20 am

WIP limit is not determined by urgency of work. If an urgent work comes, work, either team capacity is increased or team remove some work items which are less urgent

Yes, a team can mention estimation on Kanban Board, it is up to the team