In the absence of Product owner, who can take in-charge the team in sprint planning meeting?

a) Some one from PMO team
b) Scrum master
c) Person who is assigned by Product owner
d) Let the team deicide since the team is self-organized

===============================================================================================
In reality it all depends... the person who can do this job the best should do it.... but for exam... you may like to look at rule of Sprint Planning Meeting

Source : Agile Project Management with Scrum

Section :

Rule :

Sprint Planning Meeting

The Product Owner must prepare the Product Backlog prior to the meeting. In the absence of either the Product Owner or the Product Backlog, the Scrum Master is required to construct an adequate Product Backlog prior to the meeting and to stand in for the Product Owner. ......Saket Bansal