Project Framework [DP4P10] - question # 10

Posted: Fri Dec 01, 2017 7:22 am
by dipakdkulkarni1
Which of the following term BEST defines the work needed to develop a product, service, or result?
1) Product scope
2) Scope baseline
3) Scope verification
4) Project scope

Correct ans: 4 : Project scope describes the work that must be performed to deliver a product, service, or result to the stakeholders. Product scope describes the features and functions that characterize a product, service, or result.

My view: best choice should be 2 as it includes Scope base line + WBS + WBS dictionary. Work need to be done for project product should be more detailed in scope base line. isnt it ?