Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8
and an SPI of 1.25. What is a plausible explanation for that?

I have seen correct answer is 2 but how option 1 is incorrect?

1. The project was terminated early. At that time, it was over budget and ahead

2. The project has evidently been finished over budget and ahead of schedule.

Pls help

Thanks,
Suhail
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Oliver 175

Postby saket Mon Sep 28, 2015 5:01 am

I have posted this question in relevant section which we have just started... we will discuss it in that section. here is the URL :

forum.izenbridge.com/viewtopic.php?f=31&t=3041
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “Questions about Our classes, Online Classes, Webinars, Booking, Payment etc.”

Who is online

Users browsing this forum: No registered users and 2 guests