Which of the following processes may not be taking project charter as an Input?

Plan Scope Management
Identify Risks
Collect Requirement
Plan Risk Management

The Ans is given as Identify Risk.

But the Project Charter contains the list of High Level Risks. So Project Charter should be referred for analysis of these High Level risks for risk identification. Reference from PMBOK 5th ED - Page 323, 11.2.1.10.
suresi00
Contributor
Contributor
Posts: 155
Joined: Mon Nov 20, 2017 4:05 pm

Re: Quampus - 200 Questions Test - 1 [XSP/54321P/1] - Q.30

Postby suresi00 Thu Nov 30, 2017 4:37 pm

Identify risk has Proj doc as an input and Project charter is part of proj docs. Rita clearly says it takes project charter ( as part of Proj doc ) for risk identification.

In theory you are right identify risk has PC as input.

But given the questions which diagram in PMBOK didn't write PC explicitly then it is identify risk .
pradeepbhatt13
Posts: 4
Joined: Sat Mar 18, 2017 7:30 am

Re: Quampus - 200 Questions Test - 1 [XSP/54321P/1] - Q.30

Postby pradeepbhatt13 Mon Dec 04, 2017 11:13 am

Project Charter is an input to Identify Risks but it is a part of Project documents..not explicitly mentioned in PMBOK

In other 3 examples, PC is explicitly mentioned as an input..