As per the project management plan of Joe’s project, $200,000 has been assigned to it as project cost baseline. The project is planned to finish in one year. At the end of one year, on the planned date of completion, 90% of the work has been accomplished. Calculate schedule performance index for the project.


1

0.9

0.8

0

I think 200,000 is BAC as it is specified as project baseline. But in solution, 200,000 is mentioned as PV. Please explain how to find and justify this.
akitut
Posts: 17
Joined: Mon Jan 30, 2017 4:40 am

Re: Project Cost Management Mock Test

Postby akitut Wed Oct 11, 2017 6:54 pm

BAC is nothing but total budget that was planned for the project. So, here project is planned to finish in 1 year and hence it is the PV. We earned 90% of the work, i.e., EV =$180,000. Then SPI should be 0.9.

**Manish please verify if this is correct.
manishpn
Expert
Expert
Posts: 2369
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Cost Management Mock Test

Postby manishpn Sun Nov 05, 2017 11:01 am

yes thats correct
ev = 90% of 2000000
pv = 2000000
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist