PMP Practice Questions

Postby komal Thu Aug 03, 2017 2:23 pm

To maximize success for your project, you understand that identification of all stakeholders and classifying them in appropriate categories is critical. Along with sponsor you are in process of identifying stakeholders in initial stage of project. Your sponsor tells you that since the project will result in major change in organizations operations, you need to identify all potential operational stakeholders. Which from below list is least likely to be an operational stakeholder

Retail workers

Plant operations chief

Finance department manager

Call center head
kapil.bhauryal
Beginner
Beginner
Posts: 38
Joined: Fri Apr 07, 2017 3:47 am

Re: PMP Practice Questions

Postby kapil.bhauryal Thu Aug 03, 2017 2:54 pm

I will go with Finance department manager.
manishpn
Expert
Expert
Posts: 2159
Joined: Sat Jan 04, 2014 3:55 pm

Re: PMP Practice Questions

Postby manishpn Thu Aug 03, 2017 8:54 pm

komal wrote:To maximize success for your project, you understand that identification of all stakeholders and classifying them in appropriate categories is critical. Along with sponsor you are in process of identifying stakeholders in initial stage of project. Your sponsor tells you that since the project will result in major change in organizations operations, you need to identify all potential operational stakeholders. Which from below list is least likely to be an operational stakeholder

Retail workers

Plant operations chief

Finance department manager

Call center head


not sure what is the problem here, the explanation provided by izenbridge is clear enough
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 233
Joined: Sun Feb 26, 2017 6:06 am

Re: PMP Practice Questions

Postby nazrulq Mon Aug 07, 2017 10:19 pm

How about option 4. Call Centre head!
komal
Participant
Participant
Posts: 67
Joined: Wed May 31, 2017 4:34 pm

Re: PMP Practice Questions

Postby komal Fri Aug 25, 2017 6:41 am

Manish,

I could not get what izenbridge has explain in description, please explain more .
manishpn
Expert
Expert
Posts: 2159
Joined: Sat Jan 04, 2014 3:55 pm

Re: PMP Practice Questions

Postby manishpn Sat Sep 09, 2017 8:52 am

Not sure which part did you not understand.
The question is asking to identify who could potentially not be a operational stakeholders.
Operations is usually the line organization function which does repetitive tasks
refer to section 1.5 in PMBOK
if still in doubts lets discuss this in clarification session
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Mock Exams Open Questions”

Who is online

Users browsing this forum: No registered users and 1 guest