Rita - Quality Question

Posted: Thu Apr 27, 2017 9:45 am
by Wally123
A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined communications requirements, and went on to complete work packages. What should the new project manager do NEXT?

A. Co-ordinate completion of work packages
B. Identify quality standards
C. Begin the identify Risk process
D. Execute the project management plan

I have chosen C, but the answer is B

Re: Rita - Quality Question

Posted: Thu Apr 27, 2017 6:32 pm
by VCAB
Yep B is the right answer....

The project states that a budget was done (Cost Mgt--Dev Budget), and requirements collected (Scope, Collect Requirement) and WBS done Scope Mgt, Create WBS). After the budget is done the next knowledge area is Quality Mgt...

The best way to answer these question is to memorize the 47 process.....this question straight from that

Re: Rita - Quality Question

Posted: Tue May 02, 2017 6:26 am
by kapil.bhauryal
A project manager has just taken over the project from another project manager during project executing. If we consider that we are in executive its means we completed planning and option A & D seems good choice.

While Option B & C showing we are still in Planning.

Re: Rita - Quality Question

Posted: Tue May 02, 2017 8:36 am
by manishpn
I agree this is a very confusing question and I would not go with option B, since work packages are complete, it is implied that quality needs are taken care in that.
there is no clear option to choose from and explanation provided in rita is also not convincing.
the starting statement that Work package completion is done after planning is not correct, as WP creation is part of planning, also rick identification starts from beginning of the project and not dependent on quality planning.
We are in project execution phase as per situation mentioned in question, if i had to choose I would go with option D