Page 1 of 1

Stakeholder Mgmt Strategy sample question

Posted: Tue Apr 25, 2017 9:22 am
by sdutt
On your current technical project you are expecting complicated requirements.you are planning to involve stakeholders in testing as well as conducting frequent monitored meetings for clarifying requirements.This can be called

1.Stakeholder Management Strategy
2. Facilitated Workshop
3.Avoiding risks
4.Prototype

Can someone pls help solve this ? Thanks.

Re: Stakeholder Mgmt Strategy sample question

Posted: Tue Apr 25, 2017 9:48 am
by sm365
What is your answer?

Hint: This may not be Stakeholder Management Strategy question :)

Re: Stakeholder Mgmt Strategy sample question

Posted: Tue Apr 25, 2017 10:44 am
by sdutt
confused between stakeholder management strategy and avoiding risk ? Can you pls explain why this will not be stakeholder mgmt strategy?

Re: Stakeholder Mgmt Strategy sample question

Posted: Wed Apr 26, 2017 5:26 am
by sm365
What do you do to gather requirements in a complex and technical environment. Heard the terms called Quality Function Deployment, and Joint Application Development??

Re: Stakeholder Mgmt Strategy sample question

Posted: Wed Apr 26, 2017 6:20 pm
by mnajiulla
I think
2. Facilitated Workshop

Re: Stakeholder Mgmt Strategy sample question

Posted: Wed May 17, 2017 9:44 am
by seema.sonkiya
Yes.

According to the PMBOK 5 Guide Fifth Edition on page number: 114

Facilitated workshops are focused sessions that bring key stakeholders together to define product requirements. Workshops are considered a primary technique for quickly defining cross-functional requirements and reconciling stakeholder differences

Re: Stakeholder Mgmt Strategy sample question

Posted: Fri Aug 25, 2017 7:30 am
by komal
According to me it is avoiding risk.

Manish, can you please clarify if i am wrong .

Re: Stakeholder Mgmt Strategy sample question

Posted: Sat Aug 26, 2017 4:38 am
by nazrulq
Answer: Facilitated Workshop is the correct answer, I guess!

Re: Stakeholder Mgmt Strategy sample question

Posted: Sat Aug 26, 2017 12:44 pm
by manishpn
I would go with option #2 although facilitated workshops are not generally used for testing , they focus on requirement gathering.

Re: Stakeholder Mgmt Strategy sample question

Posted: Tue Aug 29, 2017 10:04 am
by Prembalaji
why cant the answer be " Stake holder management strategy "

PMBOK says

"Plan Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the lifecycle of the project, based on the analysis of their needs, interests and potential impact on project success."

where in the question talks about "testing as well as conducting frequent monitored meetings for clarifying requirements" which are two differnet phases in a project lifecycle .

Re: Stakeholder Mgmt Strategy sample question

Posted: Sat Sep 09, 2017 4:01 am
by nirajsys@gmail.com
Prem,

the key word here is "involving stakeholders for clarifying requirements"...hence the most suitable option is Facilitated Workshops.