Stakeholder Mgmt Strategy sample question

Here we discuss Freely Available PMP® mock exam questions. Internet is full of free PMP® Simulators but most of these simulators does not provide good explanation of answers, here we discuss them.
sdutt
Posts: 14
Joined: Sun Mar 26, 2017 11:27 am

Stakeholder Mgmt Strategy sample question

Postby sdutt Tue Apr 25, 2017 9:22 am

On your current technical project you are expecting complicated requirements.you are planning to involve stakeholders in testing as well as conducting frequent monitored meetings for clarifying requirements.This can be called

1.Stakeholder Management Strategy
2. Facilitated Workshop
3.Avoiding risks
4.Prototype

Can someone pls help solve this ? Thanks.
sm365
Beginner
Beginner
Posts: 26
Joined: Sat Mar 11, 2017 2:24 pm
Location: Saudi Arabia

Re: Stakeholder Mgmt Strategy sample question

Postby sm365 Tue Apr 25, 2017 9:48 am

What is your answer?

Hint: This may not be Stakeholder Management Strategy question :)
Mohammed Shabbir
PMP, ITIL Expert
sdutt
Posts: 14
Joined: Sun Mar 26, 2017 11:27 am

Re: Stakeholder Mgmt Strategy sample question

Postby sdutt Tue Apr 25, 2017 10:44 am

confused between stakeholder management strategy and avoiding risk ? Can you pls explain why this will not be stakeholder mgmt strategy?
sm365
Beginner
Beginner
Posts: 26
Joined: Sat Mar 11, 2017 2:24 pm
Location: Saudi Arabia

Re: Stakeholder Mgmt Strategy sample question

Postby sm365 Wed Apr 26, 2017 5:26 am

What do you do to gather requirements in a complex and technical environment. Heard the terms called Quality Function Deployment, and Joint Application Development??
Mohammed Shabbir
PMP, ITIL Expert
mnajiulla
Posts: 3
Joined: Mon Apr 24, 2017 2:13 pm

Re: Stakeholder Mgmt Strategy sample question

Postby mnajiulla Wed Apr 26, 2017 6:20 pm

I think
2. Facilitated Workshop
seema.sonkiya
Expert
Expert
Posts: 1762
Joined: Fri Jul 11, 2014 11:57 am

Re: Stakeholder Mgmt Strategy sample question

Postby seema.sonkiya Wed May 17, 2017 9:44 am

Yes.

According to the PMBOK 5 Guide Fifth Edition on page number: 114

Facilitated workshops are focused sessions that bring key stakeholders together to define product requirements. Workshops are considered a primary technique for quickly defining cross-functional requirements and reconciling stakeholder differences
komal
Participant
Participant
Posts: 77
Joined: Wed May 31, 2017 4:34 pm

Re: Stakeholder Mgmt Strategy sample question

Postby komal Fri Aug 25, 2017 7:30 am

According to me it is avoiding risk.

Manish, can you please clarify if i am wrong .
nazrulq
Contributor
Contributor
Posts: 237
Joined: Sun Feb 26, 2017 6:06 am

Re: Stakeholder Mgmt Strategy sample question

Postby nazrulq Sat Aug 26, 2017 4:38 am

Answer: Facilitated Workshop is the correct answer, I guess!
manishpn
Expert
Expert
Posts: 2202
Joined: Sat Jan 04, 2014 3:55 pm

Re: Stakeholder Mgmt Strategy sample question

Postby manishpn Sat Aug 26, 2017 12:44 pm

I would go with option #2 although facilitated workshops are not generally used for testing , they focus on requirement gathering.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Prembalaji
Posts: 9
Joined: Wed May 10, 2017 1:38 pm

Re: Stakeholder Mgmt Strategy sample question

Postby Prembalaji Tue Aug 29, 2017 10:04 am

why cant the answer be " Stake holder management strategy "

PMBOK says

"Plan Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the lifecycle of the project, based on the analysis of their needs, interests and potential impact on project success."

where in the question talks about "testing as well as conducting frequent monitored meetings for clarifying requirements" which are two differnet phases in a project lifecycle .
Cheers,
PJ
nirajsys@gmail.com
Participant
Participant
Posts: 72
Joined: Tue Jul 11, 2017 9:28 am

Re: Stakeholder Mgmt Strategy sample question

Postby nirajsys@gmail.com Sat Sep 09, 2017 4:01 am

Prem,

the key word here is "involving stakeholders for clarifying requirements"...hence the most suitable option is Facilitated Workshops.