Question on Change Request

Here we discuss Freely Available PMP® mock exam questions. Internet is full of free PMP® Simulators but most of these simulators does not provide good explanation of answers, here we discuss them.
catchnithi
Posts: 9
Joined: Tue Apr 04, 2017 1:38 am

Question on Change Request

Postby catchnithi Tue Apr 04, 2017 3:30 pm

Your team member during execution identify that new task is needed to be added, which was critical for feature delivery related to performance. After analysis with team member you found that no change in deadline of project because of new task. what project manager to do next?
a) Update the schedule and to add new task
b) Request for Change request
c) Immediately start working
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question on Change Request

Postby manishpn Tue Apr 04, 2017 5:50 pm

catchnithi wrote:Your team member during execution identify that new task is needed to be added, which was critical for feature delivery related to performance. After analysis with team member you found that no change in deadline of project because of new task. what project manager to do next?
a) Update the schedule and to add new task
b) Request for Change request
c) Immediately start working


I think this is not the entire question, based on information provided I would go with option A IF there is also no change in any other baseline paramater, if only schedule is not impacted but the cost or scope baseline are changed than option B will be best option
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Mock Exams Open Questions”