Question on Control Cost

Here we discuss Freely Available PMP® mock exam questions. Internet is full of free PMP® Simulators but most of these simulators does not provide good explanation of answers, here we discuss them.
catchnithi
Posts: 9
Joined: Tue Apr 04, 2017 1:38 am

Question on Control Cost

Postby catchnithi Tue Apr 04, 2017 3:27 pm

BAC for Project is 120000 with total Project duration as 6 months, after 4 months project time budget utilized 55% that is 90,000.
What it is the value of Ev,PV,SV?
manishpn
Expert
Expert
Posts: 2369
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question on Control Cost

Postby manishpn Tue Apr 04, 2017 5:54 pm

I generally do not provide answer on math unless you have done your calculation, this is best way to learn math formulla
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 257
Joined: Sun Feb 26, 2017 6:06 am

Question on Control Cost

Postby nazrulq Wed Apr 19, 2017 4:46 pm

Probable Solution.

EV =.55 * 120000 = 66000
PV = 4/6 *120000 = 800000
SV =66000-80000= -14000
SPI = 66000/80000 =.83 < 1
Behind the schedule.

Thanks.