Question on Quality

Postby catchnithi Tue Apr 04, 2017 3:26 pm

Project is in middle of execution, project manager brought external auditor to ensure all quality methodology is followed in team. Which phase of project now
a) Perform quality assurance,
b) control quality,
c) risk audit
manishpn
Expert
Expert
Posts: 2051
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question on Quality

Postby manishpn Tue Apr 04, 2017 5:56 pm

Quality Audits are part of Quality assurance process
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
sshey36
Beginner
Beginner
Posts: 26
Joined: Wed Nov 25, 2015 3:48 pm

Question on Quality

Postby sshey36 Wed Apr 05, 2017 4:36 am

Quality Control Measurements Data are important inputs to Perform Quality Assurance. What process do they come from.

1. Control Quality
2. Validate Scope
3. Quality Management Plan
4. Monitor and Control Project Work Process

My answer was wrong because it comes from Quality Control. I am not sure about the answer. It is output in Control Quality. Please advise.
manishpn
Expert
Expert
Posts: 2051
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question on Quality

Postby manishpn Wed Apr 05, 2017 6:55 am

kindly post your new question in a new thread.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Mock Exams Open Questions”

Who is online

Users browsing this forum: No registered users and 1 guest