mock question help

Postby sdutt Fri Mar 31, 2017 10:17 am

request help on the following question with expplanation pls. Thanks.

The project has been running smoothly; initiation phase is complete and the team is working on all aspects of planning. You had meetings with stakeholders several times to collect requirements and as a result, requirements documentation is almost complete, as are high-level and detailed design documents. As construction begins on the project, several stakeholders have indicated the need for changes to the requirements set. They are claiming these elements were missed in the initial requirements collection process, and they want you to add these elements to the project immediately. You perform an impact assessment and get it back to them only to hear that they are not going to allow any changes in the project budget or the timeline to complete these additional elements. What is the most effective tool that you could use to prevent this instance of scope creep?
a.Change control system
b.Configuration management system
c.Murder Board
d.Work Authorization System
manishpn
Expert
Expert
Posts: 1954
Joined: Sat Jan 04, 2014 3:55 pm

Re: mock question help

Postby manishpn Sun Apr 02, 2017 7:03 pm

bases on options provided option A is best choice. however Change control system is usually linked to contracts, else it should be change control process or change control board
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
manishpn
Expert
Expert
Posts: 1954
Joined: Sat Jan 04, 2014 3:55 pm

Re: mock question help

Postby manishpn Sun Apr 02, 2017 7:10 pm

manishpn wrote:bases on options provided option A is best choice. however Change control system is usually linked to contracts, else it should be change control process or change control board

next best option is murder board but thats usually for project selection not for individual requiremtns
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
sdutt
Posts: 14
Joined: Sun Mar 26, 2017 11:27 am

Re: mock question help

Postby sdutt Mon Apr 03, 2017 3:10 am

Thank you so much for responding. I came across this in the Edwel mock test but the correct answer as per the site was given as D ..hence got confused. So, guess this was marked wrongly.
manishpn
Expert
Expert
Posts: 1954
Joined: Sat Jan 04, 2014 3:55 pm

Re: mock question help

Postby manishpn Mon Apr 03, 2017 10:27 am

WAS is not meant to control scope creep.

Can you post the explanation provided?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Mock Exams Open Questions”

Who is online

Users browsing this forum: No registered users and 2 guests