Finish to finish relationship question

Here we discuss Freely Available PMP® mock exam questions. Internet is full of free PMP® Simulators but most of these simulators does not provide good explanation of answers, here we discuss them.
ashima11
Posts: 16
Joined: Mon Dec 19, 2016 5:40 am

Finish to finish relationship question

Postby ashima11 Mon Dec 19, 2016 4:01 pm

Activity A has a Finish to Finish relationship with activity B. Activity A has a duration of 7 days . Activity B has a duration of 5 days with a 3 day lag. What is the total duration of activity A and B.
1)12
2)9
3)7
4)8
ASGHAR ESKANDARLU
Posts: 3
Joined: Fri Dec 16, 2016 8:42 pm

Re: Finish to finish relationship question

Postby ASGHAR ESKANDARLU Mon Dec 19, 2016 5:11 pm

To me 12 days is the total activity since the Lag needs to be included in the total duration of 2 or more activities
ASGHAR ESKANDARLU
Posts: 3
Joined: Fri Dec 16, 2016 8:42 pm

Re: Finish to finish relationship question

Postby ASGHAR ESKANDARLU Mon Dec 19, 2016 5:17 pm

Now to me the test seems wrong ad in Finish to Finish activity you have Lead not lag. So none of the answers are correct.
Housam Bassal
Contributor
Contributor
Posts: 239
Joined: Fri Nov 04, 2016 7:38 pm

Re: Finish to finish relationship question

Postby Housam Bassal Mon Dec 19, 2016 6:49 pm

Watch this video , it will clarify all your doubts:
PMP | PDM -Logical Relationships or Dependencies | iZenBridge https://youtu.be/sI_mBa3y_n4
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Finish to finish relationship question

Postby saket Tue Dec 20, 2016 1:39 am

This Video should answer your queries.

https://www.youtube.com/watch?v=sI_mBa3 ... e=youtu.be
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
ashima11
Posts: 16
Joined: Mon Dec 19, 2016 5:40 am

Re: Finish to finish relationship question

Postby ashima11 Tue Dec 20, 2016 3:51 am

Yes, have gone through the video, so as per it the answer should be 10. As there is no such option so got confused. Can you confirm that the answer is 10?
vikram_unde
Contributor
Contributor
Posts: 185
Joined: Tue Aug 23, 2016 5:48 am

Re: Finish to finish relationship question

Postby vikram_unde Tue Dec 20, 2016 7:28 am

Hi Manish,

I too belive answer is 10. May I know your thoughts please?

Regards,
Vikram Unde
manishpn
Expert
Expert
Posts: 2196
Joined: Sat Jan 04, 2014 3:55 pm

Re: Finish to finish relationship question

Postby manishpn Thu Dec 22, 2016 4:08 pm

ashima11 wrote:Activity A has a Finish to Finish relationship with activity B. Activity A has a duration of 7 days . Activity B has a duration of 5 days with a 3 day lag. What is the total duration of activity A and B.
1)12
2)9
3)7
4)8


If I read the question correctly A is successor and B is predecessor
relationship are always shown in format
Predecessor ----> Successor in this
In that case answer should be 7
However since there is Lag given for B, predecessors dont have Lag so I assume the question is framed in wrong fashion and B is dependent on A, then total duration should be 10 days
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/