EAC Calculation

Here we discuss Freely Available PMP® mock exam questions. Internet is full of free PMP® Simulators but most of these simulators does not provide good explanation of answers, here we discuss them.
sheikh506@gmail.com
Posts: 7
Joined: Sat Feb 06, 2016 7:02 am

EAC Calculation

Postby sheikh506@gmail.com Sat Nov 19, 2016 6:37 am

Ques.PNG
Ques.PNG (46.16 KiB) Viewed 19024 times


Why did solution used this formula for EAC. Kindly guide.
rehanl
Posts: 2
Joined: Thu Oct 20, 2016 5:07 am

Re: EAC Calculation

Postby rehanl Mon Nov 21, 2016 4:36 am

Saqib, can you please explain how we get AC as 11. Thanks
manishpn
Expert
Expert
Posts: 2209
Joined: Sat Jan 04, 2014 3:55 pm

Re: EAC Calculation

Postby manishpn Mon Nov 21, 2016 9:55 pm

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
rehanl
Posts: 2
Joined: Thu Oct 20, 2016 5:07 am

Re: EAC Calculation

Postby rehanl Tue Nov 22, 2016 1:43 pm

Sorry Manish Sir, but don't have access to the provided link forum
seema.sonkiya
Expert
Expert
Posts: 1771
Joined: Fri Jul 11, 2014 11:57 am

Re: EAC Calculation

Postby seema.sonkiya Wed Nov 23, 2016 6:24 am

rehanl is not our regular client, we need to respond here.
vikram_unde
Contributor
Contributor
Posts: 185
Joined: Tue Aug 23, 2016 5:48 am

Re: EAC Calculation

Postby vikram_unde Wed Nov 23, 2016 8:21 am

Hi Rehanl,

Below is the similar question which will help you to understand the concept.

Mark is in execution phase of the road construction project in a town which has total duration of 12 months and work effort evenly distributed. 3 months down the line during the execution phase mark realizes that there is a change in local law which demands sound proof fencing of the road passing near the hospitals and School. This task was not foreseen and not included in cost baseline of USD Mn 18. Mark submits a Change request to CCB. While total cost budget for project is USD 25 Mn CCB approves to use USD 2 Mn for additional work from Management reserves to baseline. At the end of 5th month mark present following performance graph to Steering group. What is his Estimate at completion

a. 19
b. 20
c. 19.5
d. 21

Correct answer is a

Explanation:

Original BAC is 18 M, Which has been revised to USD 20 MN, when a Management reserve of 2Mn was approved for unforeseen work. The variance is atypical hence, at end of 5th month

PV = 7.5 (Given)
BAC = 20
EV= 8 (Given)
AC = 7 (Given)

EAC = AC+(BAC-EV) = 7+ (20-8) = 19
sheikh506@gmail.com
Posts: 7
Joined: Sat Feb 06, 2016 7:02 am

Re: EAC Calculation

Postby sheikh506@gmail.com Thu Nov 24, 2016 7:43 pm

ques.PNG
ques.PNG (81.39 KiB) Viewed 18671 times



Complete question with graph