After a study of the work processes on a project, a quality audit team reports to the project manager that irrelevant quality standards were being used by the project, which might lead to rework. What was the objective of the project manager in initiating this study?

A. Quality control
B. Quality planning
C. Checking adherence to processes
D. Quality assurance

correct answer provided is D, but here the question is asking the objective of the PM and audit initiated by PM is to check methods are obliged to project guidlines & procedure, answer should be C....pls suggest
manishpn
Expert
Expert
Posts: 2125
Joined: Sat Jan 04, 2014 3:55 pm

Re: Quality management

Postby manishpn Mon Oct 17, 2016 2:07 pm

Its not only about checking adherence but also about improving the ways of working/processes and that quality assurance its Check/Act
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Mock Exams Open Questions”

Who is online

Users browsing this forum: No registered users and 3 guests