Dear Saket,

What is the correct answer for the below Question ?

While reviewing the progress, the project manager assesses that an activity has been missed out from the implementation plan. A milestone, scheduled to be achieved within another week, would be missed with the current implementation plan.

Which of the following is the next best action for the project manager in this situation?

A. Report the error and the expected delay
B. Omit the status update on the milestone
C. Report the error and the planned recovery actions
D. Assess alternatives to meet the milestone


In the below website, it is written as D. However, as per my understanding the project Manager should report the error with priority and feels C as the BEST answer.
Please let me know the correct answer and the reason.

Source : http://www.gocertify.com/quizzes/projec ... /pmp1.html

Thanks a lot in advance.
Prem Kumar
manishpn
Expert
Expert
Posts: 2202
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Manager Milestone Assesment

Postby manishpn Mon Sep 19, 2016 7:24 am

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
happyprem
Posts: 5
Joined: Fri Sep 09, 2016 6:53 am

Re: Project Manager Milestone Assesment

Postby happyprem Tue Nov 08, 2016 8:50 am

Dear Mansih,

Thanks for the clarifications.

Regards'
Prem Kumar