Project changes

Here we discuss Freely Available PMP® mock exam questions. Internet is full of free PMP® Simulators but most of these simulators does not provide good explanation of answers, here we discuss them.
Kumar
Beginner
Beginner
Posts: 22
Joined: Tue Jul 05, 2016 1:54 am

Project changes

Postby Kumar Sun Jul 24, 2016 4:00 pm

Q1. During project executing, a large number of changes are made to the project. The project manager should:

A. wait until all changes are known and print out a new schedule.
B. make approved changes as needed, but retain the schedule baseline.
C. make only the changes approved by management.
D. talk to management before any changes are made.
Answer :B

Hint: Original schedule baseline must always be retained for monitoring progress.

Can someone pls confirm if this is right answer. My anwer is C.
chakrabortyanshu
Beginner
Beginner
Posts: 44
Joined: Thu Jun 09, 2016 1:48 pm

Re: Project changes

Postby chakrabortyanshu Sun Jul 24, 2016 4:28 pm

Option B is correct.

All the change request must go through perform integrated change control. Only approved change should be made.

Please remember CCB can have many members ( i.e. PM, SME, management representatives, stakeholders etc...)

Also PM should avoid baseline modifications unless absolute necessary and there is no other option left.

For baseline modifications, change request should be raised and should be approved by CCB.

Anshuman
manishpn
Expert
Expert
Posts: 2196
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project changes

Postby manishpn Mon Jul 25, 2016 10:02 am

Kumar wrote:Q1. During project executing, a large number of changes are made to the project. The project manager should:

A. wait until all changes are known and print out a new schedule.
B. make approved changes as needed, but retain the schedule baseline.
C. make only the changes approved by management.
D. talk to management before any changes are made.
Answer :B

Hint: Original schedule baseline must always be retained for monitoring progress.

Can someone pls confirm if this is right answer. My anwer is C.


is Hint part of question then option B is ok
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Housam Bassal
Contributor
Contributor
Posts: 239
Joined: Fri Nov 04, 2016 7:38 pm

Re: Project changes

Postby Housam Bassal Mon Dec 19, 2016 2:26 am

I think the correct answer is B, even without the hint.
Its depend on project change management plan, have saying that , PM most of time will be able to approve change requests which are not changing project baselines(Cost, schedule, and Scope), in case there is a change request lead to change to Schedule baseline (from impact analysis), he/she should present it to CCB.
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
ASGHAR ESKANDARLU
Posts: 3
Joined: Fri Dec 16, 2016 8:42 pm

Re: Project changes

Postby ASGHAR ESKANDARLU Mon Dec 19, 2016 5:58 am

Kumar wrote:Q1. During project executing, a large number of changes are made to the project. The project manager should:

A. wait until all changes are known and print out a new schedule.
B. make approved changes as needed, but retain the schedule baseline.
C. make only the changes approved by management.
D. talk to management before any changes are made.
Answer :B

Hint: Original schedule baseline must always be retained for monitoring progress.

Can someone pls confirm if this is right answer. My anwer is C.

ITEM B is the best answer to me too,since one of the main duty of the PM is to retain the schedule baseline by some compression techniques such as crashing or fast tracking :geek: