Postby Vaishali Sat Jul 23, 2016 6:08 am

You have just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:

PMP sample question 75 Network diagram

Which potential inconsistency in the diagram should you solve right now to ensure that the activities and the milestones "Start" and "A-F finished" are correctly linked?


Activity E is open ended (a "dangle") in relation to the finish milestone path convergence.
Activity F is open ended in relation to the path divergence after the start milestone.
You cannot calculate a critical path when lags and/or leads are calculated in percent.
Activities E to F need another task drawn as a hammock to calculate level of effort.

Answer is 1st i.e. activity E is open ended.

Please explain
Attachments
Network dig Qs.png
Network dig Qs.png (39.42 KiB) Viewed 1110 times
manishpn
Expert
Expert
Posts: 1874
Joined: Sat Jan 04, 2014 3:55 pm

Re: Network dig Qs

Postby manishpn Sat Jul 23, 2016 7:46 am

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Kumar
Beginner
Beginner
Posts: 22
Joined: Tue Jul 05, 2016 1:54 am

Re: Network dig Qs

Postby Kumar Sat Jul 23, 2016 1:41 pm

Hi Vaishali,

But as per the Manish cited thread, ans is C, but you mentioned ans is A. Pls confirm.

Regards,
Praveen
annieoroberts00
Posts: 5
Joined: Thu Jul 28, 2016 4:45 am

Re: Network dig Qs

Postby annieoroberts00 Thu Jul 28, 2016 11:20 am

this thread is really helpful.
manishpn
Expert
Expert
Posts: 1874
Joined: Sat Jan 04, 2014 3:55 pm

Re: Network dig Qs

Postby manishpn Thu Jul 28, 2016 12:16 pm

Kumar wrote:Hi Vaishali,

But as per the Manish cited thread, ans is C, but you mentioned ans is A. Pls confirm.

Regards,
Praveen


Hi Kumar, it should be C, lets wait for vaishali to provide an explaination on why it is A
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Vaishali
Posts: 15
Joined: Sat Jul 16, 2016 12:29 pm

Re: Network dig Qs

Postby Vaishali Sun Jul 31, 2016 8:20 am

Yes ! as per the answer given is A . I am also confused on this.
manishpn
Expert
Expert
Posts: 1874
Joined: Sat Jan 04, 2014 3:55 pm

Re: Network dig Qs

Postby manishpn Sun Jul 31, 2016 8:26 am

whats the explanation for A?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
vikram_unde
Contributor
Contributor
Posts: 185
Joined: Tue Aug 23, 2016 5:48 am

Re: Network dig Qs

Postby vikram_unde Tue Dec 20, 2016 6:56 am

I got below explanation on PM Zilla for answer : A

Actually here is lead in activity F, by 60% of duration with finish of E.

It means when F will start, E will be required to complete its 60% job and thus activity F is not its successor activity and when activity E will complete it would be considered as an open ended. But all activities or network should be converged at finish mile stone.

Hence activity E should be made connected to the finish mile stone directly by one arrow.
manishpn
Expert
Expert
Posts: 1874
Joined: Sat Jan 04, 2014 3:55 pm

Re: Network dig Qs

Postby manishpn Mon Dec 26, 2016 12:57 pm

I missed out on this aspect :)
yes its dangle activity but option C is also correct.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist