Planned value calculation

Here we discuss Freely Available PMP® mock exam questions. Internet is full of free PMP® Simulators but most of these simulators does not provide good explanation of answers, here we discuss them.
Posts: 3
Joined: Wed Jan 03, 2018 4:43 pm

Planned value calculation

Postby satya.srinivas Mon Mar 12, 2018 12:42 am

From the below question, how "Planned value" calculated?

You are the project manager who is in charge of an important project for your company. The project is 40% complete after 3 months and has cost $350,000. The budget for the project is $950,000 and is scheduled to last 8 months. How is the project performing?