Project's scope change control system

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
Saurabh
Posts: 3
Joined: Wed Dec 26, 2018 9:54 am

Project's scope change control system

Postby Saurabh Thu Dec 27, 2018 8:38 am

Please help with below question.

Which of the following statements about a project's scope change control system are correct?

A. The change control system prevents scope creep.
B. It is a system in the sense of "a set of procedures".
C. It is an automated system that provides the workflow for submitting and approving changes.
D. It is the process in which performance metrics for earned value are calculated.
E. There is no scope change control process or system; changes are handled through the Project Integration Management process

Upto maximum 3 answers are correct.
seema.sonkiya
Expert
Expert
Posts: 2332
Joined: Fri Jul 11, 2014 11:57 am

Re: Project's scope change control system

Postby seema.sonkiya Tue Jan 08, 2019 6:24 am

What is the source of this question? Please note, multiple correct questions do not come in the PMP exam.

Also, this is not a quality question.