Please help with below question.

The project manager closes out the project initiation activities with a charter signing ceremony, hosted by the project sponsor. Which of the following are valid statements regarding the relationship of the charter signing and the project communications effort?

A. Development of the communication plan does not begin until the charter is signed.
B. The project team can use the charter signing meeting to validate its stakeholder assessment matrix with the attending stakeholders.
C. The charter signing will be the first opportunity to communicate with all of the project stakeholders at the same time, since they will all have to attend.
D. The charter will identify the key members of the project team.
E. The presentation of the charter will enable the project team to secure upper management support for the project.

Upto max of 3 choices are correct
seema.sonkiya
Expert
Expert
Posts: 2292
Joined: Fri Jul 11, 2014 11:57 am

Re: Charting Signing Activity

Postby seema.sonkiya Tue Jan 08, 2019 6:23 am

What is the source of this question? Please note, multiple correct questions do not come in the PMP exam.