Postby Sud Fri Jul 11, 2014 11:57 am

A buyer has just received a final set of deliverables from the seller and finds that they do not conform to the specifications that were originally planned for. Ideally, where would the buyer expect to find documentation on how to handle non-conforming deliverables?

A. Communication Plan

B. The contract

C. Quality Plan

D. Scope Statement

Scordo. First I also marked answer as B. But on a second thought, why the Quality Management Plan not have the strategy to deal with non-conforming deliverables. Quality is "conformance to requirements!". Confused....

--Sud
yogesh
Contributor
Contributor
Posts: 142
Joined: Sat Apr 19, 2014 10:44 am

Re: Question for Discussion-Procurement

Postby yogesh Fri Jul 11, 2014 12:53 pm

Here questions abt procurement.
procurement requirements are in procurement SOW .procurement SOW is in contract
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Question for Discussion-Procurement

Postby namita Sat Jul 12, 2014 2:36 am

Agree with Yogesh. Also you need to think differently for procurements. Outside body doesn't have access to buyers quality management plan. We have to articulate all our quality criteria in contract so that seller can meet it